以下是高顿网校为大家整理的:F2会计师与企业汇总,希望对考生们有所帮助。
 
  3.3 Analysis of costs into fixed and variable elements:
 
  High-low method
  Step 1 – select the highest and lowest activity levels, and their associated costs
  Step 2 – find the variable cost per unit
  Step 3 – find the fixed cost by substitution, using either the high or low activity level.
 
  Example 1:
  Using high-low method to calculate the fixed and variable elements of the following costs:
  Month Units produced Costs ($)
  July 340 2,260
  August 300 2,160
  September 380 2,320
  October 420 2,400
  November 400 2,300
  December 360 2,266
 
  Solution:
  Step 1- Select the highest and lowest activity levels, and their associated costs
  Month Units produced Cost ($)
  Highest activity level: October 420 2,400
  Lowest activity level: August 300 2,160
 
  Step 2– find the variable cost per unit
  Total cost at high activity level – total cost at low activity level/Variable cost per unit 
  = total units at high activity level – total units at low activity level
  =( 2400 – 2160 )/(420 – 300)= $2/unit
 
 
  Step 3 – find the fixed cost by substitution, using either the high or low activity level.
  Fixed cost = (total cost at high activity level) – (total cost at high activity level x variable cost per unit)
  = $2,400 - $2 /unit x 420 units = $1,560
  High- low method with stepped fixed cost
  Sometimes fixed costs are only fixed within certain levels of activity and increase in steps as activity increases:
  · The high low method can still be used to estimate fixed and variable costs
  · Adjustments need to be made for the fixed costs based on the activity level under consideration.
 
  Example 2:
  An organization has the following total costs at three activity levels:
  Activity levels (units) 12,750 15,100
  Total cost $73,950 $83,585
  Variable cost per unit is constant within this activity range and there is a step up of $4,700 in the total fixed costs when the activity level exceeds 14,000 units.
  Required: what is the total cost at an activity level of 14,500 units?
 
  Solution:
  Unit produced Cost ($)
  Highest activity level: 15100 73950
  Lowest activity level: 12750 83585- 4700
  Variable cost = (83585-4700 – 73950)/ (15100- 12750) = $2.1/unit
  Fixed cost exceeds 14500 units = 83585 - $2.1 x 15100 = $51,875
  Total cost for 14500 units = $51,875 + $2.1 x 14500 units = $82,325
 
  High –low method with changes in the variable cost per unit
  Sometimes there may be changes in the variable cost per unit, and the high low method can still be used to determine the fixed and variable elements of semi-variable costs. The variable cost per unit may change because:
  · Prices may be forecast to increase in future periods
  · Bulk discounts may be available for purchasing resources in large quantities.
 
  高顿网校小编提醒您:信心、毅力、勇气三者具备,则天下没有做不成的事。

   ACCA官方微信    
  扫一扫微信,*9时间获取2014年ACCA考试报名时间和考试时间提醒
  
  高顿网校特别提醒:已经报名2014年ACCA考试的考生可按照复习计划有效进行!另外,高顿网校2014年ACCA考试辅导高清课程已经开通,通过针对性地讲解、训练、答疑、模考,对学习过程进行全程跟踪、分析、指导,可以帮助考生全面提升备考效果。
  
  报考指南:2014年ACCA考试备考指南
  免费题库:2014年ACCA考试免费题库
  考前冲刺:ACCA备考秘籍
  高清网课:ACCA考试网络课程