Which of the following involves comparing measures of actual progress of a project to planned progress?
a.Project planning.
b.Project scheduling.
c.Project control.
d.Project closure.
Answer:C
Choice“c” is correct.
The requirement is to identify the stage that involves comparing measures of actual progress to planned progress. Answer (c) is correct because this describes an aspect of project control. Answers (a), (b), and (d) are incorrect because they represent other stages of the project management lifecycle.